Name: 
 

Ch10 Project Scheduling: PERT/CPM



Multiple Choice
Identify the choice that best completes the statement or answers the question.
 

 1. 

Which is not a significant challenge of project scheduling?
a.
deadlines exist.
b.
activities are independent.
c.
many employees could be required.
d.
delays are costly.
 

 2. 

The critical path
a.
is any path that goes from the starting node to the completion node.
b.
is a combination of all paths.
c.
is the shortest path.
d.
is the longest path.
 

 3. 

The earliest start time rule
a.
compares the starting times of all activities for successors of an activity.
b.
compares the finish times for all immediate predecessors of an activity.
c.
determines when the project can begin.
d.
determines when the project must begin.
 

 4. 

Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W
a.
is 10.
b.
is 12.
c.
is 15.
d.
cannot be determined.
 

 5. 

Activities K, M and S immediately follow activity H, and their latest start times are 14, 18, and 11. The latest finish time for activity H
a.
is 11.
b.
is 14.
c.
is 18.
d.
cannot be determined.
 

 6. 

When activity times are uncertain,
a.
assume they are normally distributed.
b.
calculate the expected time, using (a + 4m + b)/6.
c.
use the most likely time.
d.
calculate the expected time, using (a + m + b)/3.
 

 7. 

To determine how to crash activity times
a.
normal activity costs and costs under maximum crashing must be known.
b.
shortest times with crashing must be known.
c.
realize that new paths may become critical.
d.
All of the alternatives are true.
 

 8. 

In deciding which activities to crash, one must
a.
crash all critical activities.
b.
crash largest-duration activities.
c.
crash lowest-cost activities.
d.
crash activities on the critical path(s) only.
 

 9. 

For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time?
a.
the largest EF among the immediate predecessors.
b.
the average EF among the immediate predecessors.
c.
the largest LF among the immediate predecessors.
d.
the difference in EF among the immediate predecessors.
 

 10. 

Which of the following is a general rule for crashing activities?
a.
Crash only non-critical activities.
b.
Crash activities with zero slack.
c.
Crash activities with the greatest number of predecessors.
d.
Crash the path with the fewest activities.
 



 
Check Your Work     Start Over