A network is:
?
A list of activities
?
A sequence of activities
?
A rough plan of action
?
A way of identifying what doesn’t need doing
In Problem 1, the minimum number of dummy activities is:
?
0
?
1
?
2
?
3
In Problem 1, the total minimum duration is:
?
6
?
8
?
14
?
24
In Problem 1, the critical path is:
?
AC
?
AD
?
AEF
?
BEF
In Problem 1 the earliest starting time for D is:
?
3
?
4
?
5
?
6
In Problem 1, the total float for activity C is:
?
1
?
3
?
5
?
6
In Problem 1, which activity has the minimum slope?
?
C
?
D
?
E
?
F
In Problem 1, if you were to reduce the duration of only one activity it would be:
?
C
?
D
?
E
?
F
In Problem 1 the minimum duration for the project is:
?
7
?
9
?
12
?
14
In Problem 1, the extra cost of the minimum duration is:
?
900
?
1300
?
1500
?
1700